Introduction  
                    ENGINEER  PETAR KNEŽEVIĆ, DIRECTOR OF THERMAL POWER PLANTS “NIKOLA TESLA” 
                      Price of  Noble Energy  
                    We  can calmly wait for the winter and heating season. Everything is ready.  Although the hydrologic situation is bad this year, thermal energetics has  covered the increased consumption during the past hot days. TENT, the backbone  of this process, provides one half of total power in Serbia from 3,300 megawatts  of its installed power, which represents one third of the installed power of  the Electric Power Distribution of Serbia,. In September, the nine-month plan  was realized with 105.49 percent. By 2017, strategic investments into  production and environmental protection will take place  
                    By: Aleksa Mitić 
                     
                       This winter we should not fear of shortages of  electricity. At Thermal Power  Plant “Nikola Tesla” (TENT), company that produces one half of Serbian  electricity, all planned works necessary for peaceful winter are being  finalized. And TENT is the backbone in the production of electric power and the  stronghold of Electric Power Distribution of Serbia. From its 3,300 megawatts  of its installed power, which represents one third of the installed power of  the Electric Power Distribution of Serbia, it provides one half of totally  generated power in Serbia! 
                      – Hydrologic  situation is bad this year, inflow of water is small, quantities in  accumulation lakes are low. The increased production during the past hot days  when cooling devices were working en masse, was covered by thermal energetics,  i.e. TENT, thanks primarily to continuous good quality work. In these September  days, we have already realized the nine-month plan with 105.49 percent. And  while doing this, we have conducted regular overhauls of production blocks, in  planned intervals. We had capital overhauls primarily in “Block B2” (600  megawatts), which lasted 120 days. Still, the major work was reconstruction of  electric filters. Half of the money for this was provided from donations, and  one half from our own funds – says for National  Review engineer Petar Knežević, Director of TENT for National Review, and adds: 
                      – The second major work was  replacement of the pipe system. His was the beginning of complete  revitalization of blocks “B1” and “B2”. We are finalizing the reconstruction of  “Block A4” in 60, instead of 75 days. We have increased their capacity and  fineness of milling, which was the prerequisite for optimization of combustion  process and eliminating nitrogen oxides (environmental project that we are  currently implementing). We will complete the repair of turbo aggregate of the  third block of TE „Kolubara“ with power of 60 megawatts in September, and soon  afterwards the overhaul of “Block A3“ at TE “Nikola Tesla A“ as well as TE “Morava“  of 125 megawatts will be completed, so that all plants of PD TENT wil be ready  for winter season. 
                    SAVED ONE POWER PLANT 
                     At the reconstructed “Block  A6” in power plant “Nikola Tesla”, the power was increased from 308 to 348  megawatts. This contributed to the increased energy efficiency and reduced  annual coal consumption by 150,000 tons. Testing of electrostatic filters is  currently in progress. Results are better than expected: emission of particles  is reduced to much less than 50 milligrams per cubic meter of flue gas.  
                      – Reconstruction of the plants  that survived 1990’s in a quite dilapidated condition, began a decade ago. What  has been done so far has extended the life of machines by another 100,000  hours. About EUR 450 million was invested in this, but the production was  increased by three billion and two hundred million kilowatt hours. From 16.5 we  reached more than 19 billion kilowatt hours, which is equal to a production of  a new block with the power of 400 megawatts. And in order to build a new block  from scratch, we need at least twice as much money – says Director Knežević. 
                      A large number of local and  foreign companies participated in these reconstructions. “Alstom” did the  turbine, “Rafako” boilers, some of the biggest contractors were also “Doosan  Babcock”, “Hitachi Power Europe”. Serbian companies included “Rudnap grupa”,  “Minel kotlogradnja”, “Goša montaža”, “Termoelektro AD”, “Termoelektro Entel”,  “Feromont”... More than 50 o f them. Institutes “Mihajlo Pupin” and “Nikola  Tesla”, as well as “Energoprojekt”, helped us get many jobs that had previously  been reserved for foreigners. In this way, local brains and project replaced  the imported ones, primarily in the area of automated control. Professors of  the Faculties of Electrical and Mechanical Engineering in Belgrade who selflessly participated in  everything, also played an important role. 
                      – By 2017, we are planning to  increase Power on blocks “B1”, “B2”, “A3”, “A4” and “A5”. We will primarily  work on increasing efficiency and complying with legally prescribed  environmental standards. At the same time, in this way we will increase the  production by another 3.5 billion kilowatt hours and save more than 500,000  tons of coal per year. We need 1.1 million Euros for the realization of this  plan: 600 million for ecology (desulphurization, elimination of nitrogen  oxides, completion of electric filters, control and treatment of waste  water...), and for 500 million (in an endeavor similar to the one from the  first decade of the new millennium) we will practically get another new block  of 400 megawatts. 
                    PROJECTIONS BY 2017  
                     – We are perfectly aware that  these are all steps in the right direction for relatively small investments,  but also that this will not be the final solution to the “hunger for  electricity”. Increased needs for electric can be permanently satisfied only by  new blocks in thermal power plants and hydro power plants. We could also create  some surplus, and sell electricity in the free market, primarily foreign  market, where prices are higher. We could use the profit to fill our budget and  revamp power plants. By 2017, we will squeeze additional almost seven billion  kilowatt hours from these old plants. Some of them will be shut down, because  production in them is expensive.  
                      Let us emphasize again: also  very important is the environmental project that will be realized together with  Japanese experts, and Japanese government supported it with a EUR 250 million  loan. Desulphurization plant will be built here for the first time. Instead  into the atmosphere, sulfur oxides will, by means of lime, be converted into plaster,  gypsum plaster boards, and purified flue gas will be  going out of the stack.  
                    *** 
                    How  to make clean energy 
                      Thermal power plants “Nikola Tesla” will  have their booth at the Energy Fair that will take place in Belgrade, October 12 to 14, 2011. Together with  its business partners, this company will show how to work as a team on the same  objective – improvement of the production of clean energy. 
                  – Our intention is to present projects  that are of key significance for revitalization and modernization of the  existing energy capacities, as well as those that are using different technologies  in the area of environmental protection – says director Petar Knežević. – Since  success of any project depends on team work, we wanted our long time  associates, respectable and successful companies, promote the joint plans  together with us – increase in efficiency of production of electricity and  fulfillment of legally prescribed environmental standards. 
                     |